April 2008
Presentations to prospective investors...
more...

Introduction

On these pages, technically and economically prospective sites are presented to investors by means of pre-investment studies. These studies include;

  • An introduction to the proposed design of the site, including a description of the hydrology, generation calculations, construction cost estimates and initial environmental screening.
  • A summary of the risks and opportunities regarding the marketing of electricity - based on the findings of this project.
  • A brief guide to the permitting regulations associated with the registration and construction, as well as generation, of a greenfield HPP in Georgia.
  • An indicative financial analysis, including an estimated cost reflective tariff, as well as least cost considerations and sensitivity analyses.
  • Maps, pictures and drawings of the site and the proposed designs will be provided.
  • Key characteristics of each site will be provided so as to allow for interested developers to easily adjust costs and evaluate the projects and the proposed designs.
  • Leading international hydropower engineers and environmental consultants have been responsible for the cost estimates and environmental assessment of the sites.

In total 7 sites (including 4 cascade schemes) have been studied and presented, all of them approved by the Ministry of Energy in Georgia for promotion to investors. The sites have been selected during a pre-screening process involving some 50 sites. The sites vary in size from 10MW to 638MW, but all together represent a potential considerable increase in the installed capacity in Georgia.

Site River MW GWh
Enguri Enguri 10 74
Digomi/ Ponichala Mtkvari 40.2 224
Zestaponi* Sakraula/ Kvirila 88.9 348
Mtkvari* Mtkvari 253 596
Khudoni Enguri 638 1445
Oni* Rioni 272 1475
Namakvani* Rioni 450** 1677**
Total   1752 5839

While largely un-tested, the regulatory framework for greenfield HPPs in Georgia appears favourable. In particular, the regulator allows for a full-cost tariff during a 7-year full depreciation of assets. Our calculations indicate that most of the sites, during construction and a 7-year period of full production, the tariff is highly competitive with thermal generation - the current marginal generation source.

Copyright (c) 2007 Georgia Hydropower Investment, All Rights Reserved

Web-design, Hosting, Software development, Multimedia